A practical approach to perform Technical assessment for SAP Upgrade project

$
0
0

A practical approach to perform Technical assessment for SAP Upgrade  project      

Technical assessment is the first step for any SAP Upgrade project. Initially I struggled a bit to gather all the required information in structured format as I did not get any suitable template on internet and SDN site. Finally I have decided to prepare a generic template for any upgrade project so that I can use for any client / company.  Being a SAP Basis upgrade consultant / architect, what is the most important information I need for my upgrade project, so that it will help me to smoothly execute and deliver the project on time and can cover most of the unknown(s). From my personal experience, a technical upgrade assessment is a combined effort of SAP Basis, DBA, infrastructure and functional team, primarily driven by Basis upgrade consultant or designated project manager. Since this is a technical assessment, I will not cover any functional specifications or information about affected customized programs and changes. The main focus of technical assessment is to collect information about source landscape , interfaces and target landscape  - what is going to be changed and what are  interdependencies. Finally, what tool you will use and how you will translate or implement these changes and resolve all interdependencies. A lot of upgrade projects need to perform both upgrade and Unicode migration; formally we called CU&UC (combine upgrade and Unicode conversion). So I will cover some of the critical assessment points of Unicode migration too.

A assessment report varies from company to company – it may be  a simple page , two-page-document or a comprehensive report with detail technical specifications. I have prepared the following checklist as the starting point for any SAP upgrade project as a template for technical assessment. Once again this is not for functional upgrade or functional assessment – hence this will help SAP Basis folks only.

Please share your experience if I missed something.

 

Technical Assessment Checklist

Sl No

Topic

Collected Information

Status

1

Project

 

Project is for :

 

Release Upgrade

 

Combine upgrade and Unicode migration

 

OS+DB upgrade and SAP technical upgrade.

 

 

 

Need to decide ( There are instances when client does not know whether upgrade requires OS+DB upgrade as well as platform upgrade and which path they need to follow ).

Example :

 

 

 

SAP BW 7.0 upgrade to BW 7.3

 

CU&UC from SAP Enterprise 4.7 to SAP ECC 6.0 with EHP6

 

Multi steps upgrade process: First upgrade OS + DB, stabilize the environment. Start SAP release upgrade from CRM 4.0 to CRM 7.0 –EHP2

 

Multistep scenario.

 

Completed

 

 

 

 

 

 

 

 

 

 

 

 

All other project types are straight forward except “need to decide” one.

2

Information about source system

 

SAP Release

Is it a single stack or duel stack

SPS level

Database version

DB size

OS ( Make and Version)

Hardware

Any clustering setup

Any HA / DR solution

 

 

Landscape details

 

How many systems are there on this landscape

 

Location of the servers

 

 

 

 

 

Additional App Servers

 

 

User base

Example : Source system is ECC system :

 

ECC 5.0

Single stack

SP18

Oracle 10.0.2.4

3 TB

Solaris 10

SUN M5000

No clustering

Oracle RAC for QA and Production systems.

 

 

 

 

Example :

 

Five systems landscape: Sandbox, DEV, QA, Training and Production.

 

All non-production systems are on Data Center X and production system is on Data center Y ( 50 miles apart from each other and they are connected with 1 GBPS shared network.)

 

For production system there are 20 App Servers.

 

For ECC 5.0 – 14,000 named users across North America and EUROPE.

30,000 Enterprise Portal user – for ESS/MSS applications.

Completed

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

This info will be useful for any infrastructure changes and NFS mounting issue.

3

Is there any changes to the existing environment ?

 

What are the things you need to change for the existing environment to perform this upgrade

 

SAP Release upgrade

·         Is the any minimum support pack level for this upgrade

 

 

 

 

 

·         Changes to other SAP products ( release upgrade or patches )

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

·         Solution Manager patching or upgrade required to generate stack xml

 

 

 

·         Changes to physical resource of the SAP server.

 

·         Does it require DB or OS upgrade ?

 

 

 

 

 

Combine Upgrade and Unicode migration projects.

 

(Printer is a key area need to address carefully in case of Unicode migration.).

Example

 

 

 

 

 

 

 

 

·         Yes ( for example ) upgrade the 640 kernel to 640_EXT while upgrading form ECC 5.0 to ECC 6.0 (EHP6) and that will support higher release of DB and OS.

 

·         Based on changes – it may trigger another SAP product to change. For example,  if you like to upgrade to ECC 6.0 with EHP6 and you have CRM 4.0 system, there is a strong possibility that you have to upgrade your CRM system too. So gather information about all changes.

 

Another example is : if you upgrade your CRM system to CRM 7.0 EHP2 and your connected backend system is ECC 6.0  with EHP3, you need to apply patches for PI_Basis on your ECC system for interoperability.

 

·         Apply patch for Solution Manager ( for example to generate EHP6 stack xml you need to have minimum SPS23 for Solution Manager ).

 

 

 

·         Does it require more memory and CPU to cover your downtime?

 

·         In certain upgrade scenario, you have to upgrade OS or DB or both before upgrade ( verify with PAM)

 

 

Perform CU&UC from SAP R/3 4.6 to SAP ECC 6.0 EHP5. Verify all third party software’s Unicode compatibility. Check all printers. 

 

Changes to physical resource of the SAP server – Memory and CPU cores. Database size and storage.

 

Changes to security and authorization. Specialize privilege require to perform upgrade.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Check interoperability OSS notes like :

 

Note 1388258

Note 1064635

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4

High level reason for changes

 

Upgrade projects

 

 

 

 

Upgrade SAP release to the latest release to reduce licensing and maintenance cost, as extended maintenance support for SAP XXX product will end by first quarter of this year.

 

5

Information about SAP Interfaces and Add-ons :

 

Collect information about all SAP systems connected through RFC and SSO setup.

 

 

 

 

Is there any NFS file shared between source system and any other SAP system (viz  with PI system ).

 

 

Is there any enterprise level / embedded search functionality has been configured?

 

Is there any FPN (Federated Portal Network ) configuration exist. ( This is useful in case of upgrade of Portal or duel stack system )

 

 

 

UME ( User management engine ) – this is useful in case of Enterprise portal.

 

Does your system use any external knowledge management or document management system using?

 

Does your system use any archiving solution

 

Does your system use any radio frequency device

 

 

Add-ons :

Add-on play a critical roles in case of upgrade and Unicode migration, so find out all SAP and third party Add-ons and their compatibility after upgrade or Unicode migration :

 

Does your system use any SAP Add-on ?

Current release and status

Unicode compatibility

Upgrade require ?

 

Third party Add-on

Does your system use any third party  Add-on ?

Current release and status

Unicode compatibility

Upgrade require ?

Any additional licensing cost ?

 

 

 

Example :

Current source system is ECC 6.0 is connecting to

SAP BW 7.0 system

CRM 7.0

Portal 7.01 (ESS/MSS)

PI 7.1 system

Yes. NFS between PI and ECC system.

 

 

 

 

 

TREX 7.0 is using. Does it require to upgrade current TREX?

 

 

Collect all info about all FPN systems and gather info if you upgrade one system whether federation will work or not. Does it require to upgrade other system(s) too ?

 

 

Local UME or external UME – like LDAP or other ABAP system.

 

 

Information about external system / location for document management.

 

 

Archiving solution like IXOS ?

 

 

Radio frequency devices are configuring through SAP Telnet.

 

 

 

 

 

 

 

 

 

Example :

BI-CONT, ST-PI

 

 

 

 

Example :

BizRight Approva.

 

 

 

 

 

 

 

 

 

 

Need clarification from functional team.

6

Information about Non-SAP interfaces :

Non SAP interfaces are more critical for Upgrade and Unicode conversion projects. Compatibility issue with upgraded SAP release is one of the major concerns. So important question will be whether existing third party software will run with upgraded SAP release or not ? Typical you need to gather info as follows :

 

Is there any third party software connected to SAP system ?

 

 

 

Any upgrade required?

 

How it connects to SAP system

 

Is there any FTP / SFTP transfer to/from SAP system that require SSH key to exchange.

Non SAP interfaces are : Example :

 

 

 

 

 

 

 

 

 

 

 

 

There are three four third party software ( Vertax, TexWare, Seeburger and XiPay ) connected to SAP.

 

Must be Unicode compatible.

 

RFC (TCP/IP) connection

 

 

SFTP communication with two banks (using Unix level scripts). One way communication.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

This information will be useful in case of any hardware changes as you need to regenerate SSH key .

7

Business Expectation :

 

Being a SAP Basis consultant, in many projects we do not know why company has decided to upgrade this SAP release or what is the business justification of this upgrade project. However, it is important to know the driving force for this changes.

 

This is high level objective of the projects

 

Upgrade projects

 

 

 

 

 

Upgrade and Unicode migration projects.

Example :

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Upgrade SAP release to current version to reduce licensing and maintenance cost, as extended maintenance support for SAP XXX product will end by first quarter of this year.

 

 

Expanding business to new countries ( having different languages) , so converting system to Unicode will help in this aspect. Performance improvements of SAP system  and reduce licensing and maintenance cost, as extended maintenance support for SAP XXX product will end by first quarter of this year.

 

 

 

8

Expected downtime

 

This is the expected downtime time from the business.

Example :

Business can give maximum production downtime of 36 hrs.

 

This is one of the critical information to plan for production cutover activity and you have to optimize downtime to fit into this time frame.

 

In certain instances downtime is determine based on trial run of the upgrade.

 

9

Resource requirement (Hardware  and Software)

 

Hardware requirement :

 

AS per SAP sizing guide, identify H/W requirements. This is a preliminary estimate and there is a possibility to adjust ( 20 -30 %).

 

Upgrade Projects

 

 

 

 

 

 

 

Upgrade and Unicode migration projects

 

 

 

 

 

 

 

 

 

 

 

 

Software requirement :

 

All media require  to perform the upgrade.

 

Upgrade projects

 

 

 

 

 

 

 

Upgrade and Unicode migration projects

Example :

 

 

 

 

 

 

 

 

 

For upgrade projects

·         30 % more memory

·         30 % more CPU cores

·         20 % more database space

·         100 GB additional space for SAP file system.

 

 

 

For upgrade & Unicode  projects

·           40 % more memory

·         40 % more CPU cores

·         40 % more database space

·         1 TB additional space for Unicode export /import

·         Additional App servers for – SAP distribution monitor

·         100 GB additional space for SAP file systems.

 

 

 

 

 

 

 

Upgrade projects – check the PAM. Also identify any OS or DB upgrade require?

 

Check / identify any third party software / Add-on need upgrade

 

 

 

For CU&UC projects -- check the PAM. Also identify any OS or DB upgrade require ?

 

Check / identify any third party software / Add-on need upgrade

 

Reference :

 

PAM ( Product availability matrix ).

 

SAP quick sizer

10

Expected Target environment

 

Expected Target environment in terms of SAP release, hardware platform, OS and Database.

 

Upgrade projects

 

New SAP release along with OS and Database detail.

 

 

 

 

 

Upgrade and Unicode migration projects

Example

 

 

 

 

 

 

Target SAP release is  ECC 6.0 with EHP6. Database IBM DB2 LUW 9.7 and OS: AIX 6.1. Upgraded system must contain same number of App Serves.

 

All connected SAP systems BW, CRM, SRM and EP etc must work without any error.

 

Target SAP release is  ECC 6.0 with EHP6. Database IBM DB2 LUW 9.7 and OS: AIX 6.1

 

All connected SAP systems BW, CRM, SRM and EP etc must work without any error. All third party software must work  correctly.

 

 

Customize Tablespaces

 

Now-a-days it is common to have user-defined tablespaces in large SAP system ( as lot organizations moved out very large table from standard package, like APPL1, APPL2  to customize one). Collect all info related to customize tablespaces ( and this info will be very useful for Unicode migration export/import ).

 

Is there any customize tablespace exist ?

TABART or Data Classes are correct or not ?

Example

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Yes. There are five user defined tablespaces.

Verify tablespace mapping and definition of TABART or Dataclass.

 

11

Infrastructure support

 

Support from the infrastructure team is crucial for any Upgrade projects. You need to identify available expert or resource in the respective areas :

 

Hardware and OS support

 

 

 

 

DBA support

 

 

 

Network team support

Example

 

Outline info about infrastructure team

 

 

 

 

In house support team for OS or hardware and storage are available however the support team sits in different location.

 

There is no separate DBA team – you need perform all database related activity.

 

Network support team is supporting from offshore.

 

12

Known constraint  and assumption

 

Constraints

 

 

 

 

 

 

 

Assumption

 

 

 

Known constraints ( example )

Strict downtime window of 24 hours. No in-house expert / support team for database.

 

No structured documentation for SAP landscape info and third party software connected to SAP.

 

Assumption : ( example )

Current backup system will work in case of emergency.

Current team has all required authentication info – including all DDIC password and J2EE_ADMIN password.

 

13

Tools and technique

Identify specific tool need to use for upgrade or migration projects :

 

SAP Upgrade project

 

 

 

 

 

 

 

 

 

 

Combine Upgrade & Unicode migration projects.

Example :

 

 

 

 

Use ASU tool.

Use Solution Manager (SOLAR_PROJCE_ADMIN) for project admin and change control.

 

Which SAP upgrade tool will be appropriate for this upgrade – is it SAPEHPI or  SUM (SAP Upgrade Manager)  or SOLMANUP ( for solution manager upgrade).

 

 

Use standard predefine configuration mode for all non-production systems and use customize mode where you can select number of Rtrans, number of R3load and number of batch processes.

Use SAPINST to perform Unicode export/import for all database less than 200 GB.

Use Migration Monitor to perform Unicode export/import for all database less than 1 TB and greater than 300 GB.

Use Distribution monitor to perform Unicode export/import for all database bigger than 1 TB.

 

14

Unicode / Non-unicode

 

For any CU&UC project, better to determine whether the existing non Unicode system is “single code page” or “MDMP” ? How many additional languages has been installed on the system.

Based on whether single code page or MDMP, Unicode migration time and effort as well as process will change.

 

Run the report RSCPINST or I18N to verify this settings

Also check SMLT.

 

15

Any changes to SAP level security and authorization

 

Based on SAP product and upgrad release there will be number of changes to security and authorization area. Note down all major known changes.

 

SAP Upgrade project

Example

 

 

 

 

 

 

 

 

 

Upgrade projects

Example :Upgrade from CRM 4.0 to CRM 7.0 (EHP2)

·         New CRM WEBUI

·         Concept of business role + UI role

 

16

Change management process

 

Is there any change management system in place ?  Change management process will play a vital role for project schedules and mile stone dates.

Example :

 

Company XXX is using “Remedy” change management system for any changes to OS level – including all Kernel parameters and file system adjustment. For all non-production system approval is require from SAP Basis Manager and Infrastructure manager.

 

For any database changes, raise a helpdesk ticket to DBA team.

 

17

Number of effectedstructures or programs

 

This is one of the key questions – business team and development team is always interested. However there is no straight forward answer for this question – until and unless use some third party tools or perform the first upgrade on Sandbox system.

 

 

 

Note down all SPDD and SPAU objects from the first test upgrade.

 

18

Key contacts

Key contact from project sponsored, infrastructure team and entire team.

 

 

Conclusion : This is a generic template, all examples must be replace with your actual data. This technical assessment document is primarily developed to gather info related to ECC upgrade and upgrade of any component of NetWeaver stack like – BW, SRM, CRM, SCM and Enterprise Portal. It may work for other SAP products; so far I did not try for other SAP products, except Business Objects ( BOBJ 4.0) upgrade.


EHP5 to EHP7 Upgrade: Preprocessing error MAIN_SHDIMP/SUBMOD_SHDIMP/SHADOW_IMPORT_INC

$
0
0

Dear ALL ,

 

I am performing an SAP update ECC6 EHP5 to EHP7 and I got stuck at Preprocessing phase with the following error:

Checks after phase MAIN_SHDIMP/SUBMOD_SHDIMP/SHADOW_IMPORT_INC were negative!

 

Last error code set: Detected 10 errors summarized in 'SHDALLIMP.ELG'<br/> Calling 'D:\SUM\abap\exe/tp' failed with return code 8, check D:\SUM\abap\log\SAPup.ECO for details

 

ERROR: Detected the following errors due to error summary in SHDALLIMP.ELG:

  1. D:\SUM\abap\log\SAPK-60523INLOCHRSAE.PRO:

3WETW000   Key field is not in NTAB.

3WETW000 different nametabs for table T7AEPBS22 (field OPR).

4 ETW000       Field is not in NTAB.

4 ETW000      table T7AEPBS22: entry in DB is 28 bytes smaller than in file.

4 ETW000      ... ignoring such differences.

2EETW000 key field T7AEPBS22-ITEXT contained the value 'Actions                  ': key field T7AEPBS22-ITEXT missing, key is truncated.

2EETW000 key field T7AEPBS22-SUBTY contained the value '8G': key field T7AEPBS22-SUBTY missing, key is truncated.

2EETW000 key of table T7AEPBS22 (0000000Actions                  8G) only valid up to offset 14 (in bytes). It's better to skip it.

2EETW000 key field T7AEPBS22-SUBTY contained the value '0450': key field T7AEPBS22-SUBTY missing, key is truncated.

2EETW000 key of table T7AEPBS22 (0002001                         0450) only valid up to offset 14 (in bytes). It's better to skip it.

 

3WETW000   Key field is not in NTAB.

3WETW000 different nametabs for table T7AEPBS22 (field OPR).

4 ETW000       Field is not in NTAB.

 

 

Choose action:

*Repeat phase MAIN_SHDIMP/SUBMOD_SHDIMP/SHADOW_IMPORT_INC to continue at the point it stopped

*Exit program

 

Initialize phase MAIN_SHDIMP/SUBMOD_SHDIMP/SHADOW_IMPORT_INC to restart it from the beginning

INT *

 

 

Please help me solve this issue

 

Best Regards,

 

SAP ERP 6.0 EHP 6

$
0
0

Hi Everyone!

 

Before anything else, i would like to say that I'm a student very eager to learn and understand all that i can from SAP, but still a STUDENT, so please take it easy on me and i apologize in advance if i don't catch up so quickly,

 

My Questions are:

1. What are the hardware/software requirements or specifications for implementing Enhancement Pack 6 on an existing SAP ERP 6.0? any ideas on the cost?
2. Are the rumors about an SAP ERP 7.0 true? or is it a version 7.0 of SAP EHP?

 

Thank you in Advance!

Stuck at pre-processing stage for 4.7 to ECC6 Ehp6 upgrade

$
0
0

Hi Experts,

 

In the process of upgrading from 4.7 to ECC6 EHP6. The upgrade wasstopped at the pre processing stage with the error

 

MAIN_SHDPREPUT/SUBMOD_SHDALIASDEL/SCEXEC_DEL_ALI!

 

 

I upgraded & downgraded the the r3tans & tp versions but error remain
please find the attached log files

Upgrade tool to be used

$
0
0

Experts,

 

It would be great if you can clear a confusion.

 

I would be upgrading R/3 4.7 to ECC 6.0 EHP 5. As per EHP 5 upgrade guide and note 1863907 (note suggests that SAPup needs to be used for release upgrade and SUM for updating or upgrading EHP levels) the tool that should be used is SAPup. However I read that SUM can be used to upgrade R/3 4.7 to ECC 6.0 EHP 6.

 

Please throw light on my below doubts -

 

- Is SUM tool only used when EHP 6 comes into picture (like updating or upgrading to EHP 6)?

 

- Can SUM tool not be used to upgrade R/3 4.7 to ECC 6.0 EHP5 or any update or upgrade to EHP 5?

 

Regards,

Sourabh Majumdar

PSAPSR3702 not empty after ERP6 Ehp6 upgrade - 8 tables still in place

$
0
0

Hi,

 

after completing the ERP Ehp5 --> Ehp6 upgrade using the SUM tool I found that the old PSAPSR3702 tablespace still had 8 tables residing in it. These were :-

 

TTREE

TTREED

TTREEI

TTREEN

TTREEP

TTREET

TTREE_APPL

TTREE_FLNK

 

I have encountered a similar issue in the past when upgrading R/3 4.7 to ERP 6 Ehp5 where some tables were left in the PSAPSR3620 tablespace post upgrade. OSS 674070 was actioned in this case to resolve.

 

This note however is specific to upgrades from the r/3 4.7 release and does not seem to work in my case where the upgrade source release was ERP6 EHp5.

 

Has anyone seen anything similar with their upgrade process to Ehp6 from Ehp5.

 

I'm thinking about using brtools to reorg these tables into the PSAPSR3731 tablespace which will then leave the PSAPSR3702 tablespace empty and it can then be dropped as per upgrade guide.

 

brspace -p init<SID>.sap -s 20 -l E -f tbreorg -a reorg -mode online -s PSAPSR3702 -o SAPSR3 -t TTREED -n PSAPSR3731

 

Before I do this it'd like to check if anyone else has encountered the same issue with tables left in PSAPSR3702 post upgrade and if my solution is the preferred way to correct.

 

Regards,

 

Brian.


MAIN_INIT/CHECKCDMOUNTS: Export DVD for product ERP

$
0
0

Hi guys,

 

Current action:

Upgrade from SAP R/3 4.6C to SAP ERP 6.0 EhP4 / NW 7.01

 

Upgrade is stopped at MAIN_INIT/CHECKCDMOUNTS asking for:

«Enter at least the mount point for the DVD titled "Export DVD for product ERP"»

 

We've provided the requested media:

C:SAPMEDIASAPUPGEXP51036903_1

LABEL.ASC

SAP:::MM::D51036903_1

 

and

 

C:SAPMEDIASAPUPGEXP51036903_2

LABEL.ASC

SAP:::MM::D51036903_2

 

We get the following error:

 

The requested Data Carrier is not mounted on any of the mount points you entered.

class com.sap.mid.mxp.UnspecificDataCarrierRequest:com.sap.sdt.bootstrap.BootStrap@2c641e9a

incompatible with class java.io.File:null

Please enter mount points for the DVDs required for the upgrade.

Enter at least the mount point for the DVD titled "Export DVD for product ERP"

 

Any ideias?

 

Thank you.

 

Bruno Pereira

 

Error at MAIN_UPTRANS/STARTSAP_PUPG

$
0
0

Hello,

 

at implementing EHP 6 SUM fails in PHASE MAIN_UPTRANS/STARTSAP_PUPG.

 

At PHASES.LOG I get the following error:

1 ETQ399 SYSTEM MANAGER: Contents of instance list. Instance Number: 00.

1EETQ399 SYSTEM MANAGER: Instance Q61 00 not found

2EETQ354 Starting system failed, rc="-1"

 

The strange effect is, that the SAP System is startet. The service SAPSTARTSRV is running. I have stopped the system several times with the following comands:

- sapcontrol -nr 00 -function StopWait 300 10

- SAPup stoporig

- stopsap R3

 

Then I have stopped SAPSTARTSRV, SAPCCM4X and SUM

After this I did a "cleanipc all remove"

Then I have started the system an SUM again and got the same error.

 

I found several notes where the SAP did not start but no one where the system runs but the error occurs.

 

I found following strange behavior:

hges2100:q61adm 24% /saptmp/SUM/abap/bin/SAPup rootdir=/saptmp/SUM/abap stoporig

Waiting 20 seconds for proper system stop...

hges2100:q61adm 25% /saptmp/SUM/abap/bin/SAPup rootdir=/saptmp/SUM/abap checksysstatus

ERROR: Original system should be up, but appears to be down!

hges2100:q61adm 26% /saptmp/SUM/abap/bin/SAPup rootdir=/saptmp/SUM/abap startorig

Starting service ...

hges2100:q61adm 27% /saptmp/SUM/abap/bin/SAPup rootdir=/saptmp/SUM/abap checksysstatus

Original system is down.

 

I can logon to the system now!

 

Does anyone know this behaviours?

How does the "SAPup checksysstatus" get the information if the system is running?

 

Best regards

Andreas


issue after upgrade EHP7

$
0
0

Hi

 

we finished upgrade ECC6 EHP5 to EHP7 ( OS : windows 2008 R2 / DB : SQL 2008 R2 ) on DEV /QAS systems There are some problems such as :

 

 

1 - The appearance of Overlap in some screens . despite the presence of these screens a good on the client 000 .

 

 

2- when trying to System Copy ( Export/import ) occur problem and didn't completed

    (Unloading of 'SAPNTAB' export package: ERROR ) please find attached for more details .

 

Best Regards,

Posting Goods issue in different UOM than Delivery

$
0
0

I want to post goods issue which will be in different UOM than delivery through BAPI/FM.

 

Any Function module or BAPi will be helpful with the list of parameter to be passed.

I tried using ws_delivery_update with quantity passed in BASE UOM(Different than Sales UOM on delivery/Order) , but it always post material document(Godds issue) in sales UOM.

 

Is there some customizing which controls UOM on material document ?

Or i am missing something here  ?

Please suggest something.

 

Thanks in Advance.

4.6C Upgrade to ECC 6.00 EHP6 (CU&UC)

$
0
0

Hi all,

 

we are planing to Upgrade our SAP System.

 

Now we are on Windows Server 2003 x86, MaxDB 7.7 and non Unicode.

 

I´ve read the Upgrade Guides and CU&UC Guides.

 

But some Questions are left:

 

When i upgrade to EHP6, wich Netweaver Version is it? (7.02 or 7.31)?

 

And wich Tool should i take? In the (CU&UC) Guides is it SapUp. Or should i take the SUM?

 

I found the Upgrade Master from 4.6C to ECC 6.00 and also the Upgrade Export. But only without EHP.

 

I´ve read that i can go directly from 4.6C to ERP 6.00 with EHP6. Is that correct?

 

If it is possible to upgrade directly, where can i find the Upgrade Export to EHP6?

 

Can i use the normal EHP6 Export (for a new SAP Installation) from the Download Center for the Upgrade?

 

And at the end we want to move from MaxDB to Sybase ASE.

 

So in short:

 

From SAP 4.6C non Unicode to ECC 6.00 EHP6 Unicode.

 

Please provide me the best Solution.

 

Thanks in advance.

 

Marcel

SP stack implementation with SUM: incorrect detection of the system technology

$
0
0

Hello,

 

I would like to implement support package stack 24 (10/2013) with SUM on a SAP ECC 6.0 ABAP system, but when I start the SUM tool,

on the bottom of the first screen, in the "Detected SAP NetWeaver system" section the "System Technology" is "Dual Stack system" .

 

Unfortunately, I don't know anything about the history of the instance, I only noticed that this was a dual stack system in the past,

in the meantime the Java part was incompletely uninstalled and now only the ABAP instance and the Central Services instance

(Message Server + Enqueue Server) are up and running.

 

My question is, is there a way to make an adjustment in the configuration of SUM to display the correct system technology

(Single Stack ABAP system) without doing the "cleanup" after the incomplete unistallation of the Java part?

 

Thank you in advance for your help.

 

Kind regards,

Noemi

Severe error(s) occurred in phase MAIN_SHDPREPUT/SUBMOD_SHDALIASDEL/SCEXEC_DEL_ALI!

$
0
0

Hi Experts,

 

During upgrade from ECC 5.0 to EHP 7 i'm facing one error at Preprocessing phase as below:

 

Severe error(s) occurred in phase MAIN_SHDPREPUT/SUBMOD_SHDALIASDEL/SCEXEC_DEL_ALI!

Last error code set: 6 processes failed, check 'SCEXEC_D.*' for details

 

On checking details under log file SCEXEC_D.* getting description as :

Starting subprocess with PID 25803 in phase 'SCEXEC_DEL_ALI' at 20140115132700

    ENV: DIR_LIBRARY=/usr/sap/QTY/SUM/abap/exe

    ENV: LD_LIBRARY_PATH=/usr/sap/QTY/SUM/abap/exe:/usr/sap/QTY/SUM/jvm/jre/lib/amd64/server:/usr/sap/QTY/SUM/jvm/jre/lib/amd64:/usr/sap/QTY/SUM/jvm/

jre/../lib/amd64:/usr/sap/QTY/SUM/abap/exe/:/oracle/client/11x_64/instantclient

    ENV: NLS_LANG=AMERICAN_AMERICA.WE8DEC

    ENV: ORACLE_BASE=/oracle

    ENV: ORACLE_HOME=/oracle/QTY/112_64

    ENV: ORACLE_SID=QTY

    ENV: PATH=/usr/sap/QTY/SUM/abap/exe:/oracle/QTY/112_64/bin:.:/home/qtyadm:/usr/sap/QTY/SYS/exe/run:/usr/lib64/qt-3.3/bin:/usr/local/bin:/bin:/usr

/bin

    ENV: SAPDATA_HOME=/oracle/QTY

    ENV: SAPSYSTEMNAME=QTY

    ENV: auth_shadow_upgrade=1

    ENV: dbms_type=ORA

    ENV: dbs_ora_schema=SAPQTY

    ENV: dbs_ora_tnsname=QTY

 

EXECUTING /usr/sap/QTY/SUM/abap/exe/tp  pf=/usr/sap/QTY/SUM/abap/var/EXDBNEW.TPP execdbscript QTY -x ../var/PTALDR02.XQL DBEXECNONT DBEXECNOCHECK

This is tp version 380.10.11 (release 740)

ERROR: uncaught internal error:

ERROR: EXIT(16) -> process ID is: 25803

HALT 20140115132705

 

tp returncode summary:

 

TOOLS: Highest return code of single steps was: 16

ERRORS: Highest tp internal error was: 0234

tp finished with return code: 234

meaning:

  uncaught error -> function err_exit called

 

Referred SAP Notes : 526600,152420 .Still issue persists and also find attached files for more on issue.

Please help me to resolve.

 

 

Regards,

Gaurav Rana

Is R3load used in Upgrade process

$
0
0

Hi all,

 

During Upgrade in CONFIGURATION PHASE when we select

 

> MANUAL SELECTION OF PARAMETERS & provide values R3load is by default 3

 

I am pretty confused where R3load is used in Upgrade process

 

Why is R3load not mentioned in the Upgrade Guide if it is effectively used

 

SAP ERP 6.0 Including Enhancement Package 4 Support Release 1 ABAP

Based on SAP NetWeaver 7.0 Including Enhancement Package 1

 

Pls advice on the following

 

-Rahul

ERP Upgrade 2-system landscape

$
0
0

Dear experts,

 

Kindly asking your guidance in the following query.

 

What would be the best approach and the steps in a 2-system landscape (DEV,PRD) upgrade (ERP 2004 to ERP 6.0 EHP5, Win 2003/MSSQL 2005), to be able to achieve dual maintenance?

 

Any pointing to useful documents/blogs/discussions would be very appreciated also.

 

Thanks and regards,

Shkelzen


How to upgrade SAP from ECC 6.0 EHP0 to ECC 6.0 EHP7 with database Oracle 10g ?

$
0
0

I am a newbie in SAP. Please Help.

 

 

Thanx and Regards,

kamal

Can anyone tell if EHP7 has released ?

$
0
0

I am newbie in sap please help me to confirm ???

 

thanks and regards,

kamal

Is ther any things like ECC6.0 EHP0 or its only ECC6.0 ???

$
0
0

I am confused about EHP0, If it is any "SAP ECC6.0 EHP0" available or we can only say it as ECC6.0 ????

 

I am newbie in SAP Please help me.

 

 

 

thanks and regards,

kamal

R/3 4.6 C to ECC 6.0 Upgrade

$
0
0

We are currently running R/3 4.6C on AIX with Oracle 9i. We have to upgrade to ECC 6.0 and migrate to SQL Server / Windows eventually.

 

we are planning to Upgrade the DB to 10G, Unicode conversion and upgrade to ECC  and finally migrate to SQL Server, Windows. Can you comment on this strategy?

 

Anybody suggests the Pre-Reqs needed for DB and/or SAP support packs to Upgrade and Unicode Conversion?

 

Please share any OSS notes/ documentation regarding Pre-reqs.

 

Thanks in advance,

Vidyadhar

Checks after phase MAIN_SHDIMP/SUBMOD_SHD2_RUN/RUN_RADCUCNT_ALL2 were negative!

$
0
0

Hi,

 

During upgrade pre processing phase i got below error:

 

Checks after phase MAIN_SHDIMP/SUBMOD_SHD2_RUN/RUN_RADCUCNT_ALL2 were negative!

Last error code set: Single errors (code &lt;= 8) found in logfile 'RADCUCNTALL2.ELG'

 

ERROR: Batchjob RADCUCNTUPG on shadow system failed. Detected the following errors:

# /usr/sap/QTY/SUM/abap/log/RADCUCNTALL.QTY:

          3 EDO551 Level "99":"4" objects assigned, "33" less dependencies

          3 EDO551 Level "100":"22" objects assigned, "18" less dependencies

          3 EDO551 Level "101":"15" objects assigned, "3" less dependencies

          3 EDO551 Level "102":"2" objects assigned, "0" less dependencies

          3 EDO653 Graph_Analysis: "91.595" objects on "102" topological levels

          1EEDO538 DD sources table "YMUS~" could not be read

          1EEDO538 DD sources table "VTEST11~" could not be read

          1EEDO538 DD sources table "VTEST10~" could not be read

          1EEDO538 DD sources table "VBLOG~" could not be read

          1EEDO538 DD sources table "UTAB~" could not be read

          1EEDO538 DD sources table "TERCL~" could not be read

          1EEDO538 DD sources table "TERCL3~" could not be read

          1EEDO538 DD sources table "TERCL2~" could not be read

          1EEDO538 DD sources table "T512CLU~" could not be read.

 

For resolution i followed SAP Note 765475 for Unicode Conversion Troubleshooting and found


"‘Table type XXXXXX: Row type YYYYYYY does not exist. Nametab cannot be created.'

1EED: DD sources table “xxx” could not be read.

Runtime object for "TABINCSTR" could not be generated. Tabletype UMGTTABNM: Linetype UMGSTABNM does not exist. Nametab not created.

Solution: You can ignore such error messages for the following obsolete tables:

TABINCSTR, H_DC1RULES, DHISTSTR, BDLYTCC, UMGTTABNM, UMGTCPFLD, UMGTCHKP"

 

 

Please guide me more for the specified issue.

 

Regards,

Gaurav Rana