Hi Experts,
I am performing SCM 7.0 to SCM 7.0 EHP3 upgrade using SUM tool.
Initialization and Extraction phases are over and Its in configuration phase
Should I choose "Standard" in the "tool configuration"
How to define the parameters for procedure?
is there any calculation for it?
should we go with default value or should be changed/assigned with value?
Parameters are given below
"Enter the max no of Background WP during the update"
BATCH PROCESS uptime ...?
BATCH PROCESS downtime ...?
" Enter the max no of DDL processes
DDL processes uptime ...?
DDL process downtime...?
"Enter the max no of parallel import process"
R3TRANS uptime...?
R3TRANS Downtime ...?
Enter the mx no of parallel table import process"
"R3LOAD uptime ..?
R3LOAD Downtime ?
"Parallel phases to run"
Uptime ...?
Downtime...?
Note : RZ04 is inactive for operation modes
System available dialog WP's - 17
system available Background WP's - 7
system available update Wp -3
Memory - 32 GB
No of CPU processor - 6
Please let me know the values can be assigned to each question marks in the above.
I will appreciate your help and guidance
Thanks a ton